Wall Framing

The weather has been against us, but works are slowly progressing upwards, with structural steel framing up and timber wall frames in lower level almost complete.

img_3213

Lower level corridor/stair well looking out rear door to garden. TV/tatami room to left, master bedroom and ensuite to right.

img_3210

Tatami room looking out to garden.

 

img_3217

Awaiting waterproofing and core-filling of block work retaining wall.

Advertisements

Footings Completed 

20 July 2016. All hands on deck for slab pour and concrete stump placing. Wirecon concreting brought in seven concrete trucks to fill the slab and stump holes. The guys were using the helicopter trowel for over three hours to achieve a burnished finish on the slab.

14 July 2016 under slab plumbing, trenches and form work

14 July 2016 blinding concrete placed

20 July 2016 Under slab insulation also to sides placed, membrane and mesh

Concrete placed including set down for ensuite and block retaining walls

Placing stumps


Concrete pump truck